Hanoi has set itself a hard deadline. Before March 1, 2026, the city's People's Committee (Uy ban nhan dan, the local government body that approves and oversees real estate projects) has been told to definitively resolve every stalled non-budget housing project still sitting on its books. The number on the table is not small. Hanoi has counted 404 stalled residential developments, and as of late 2025 it had only fully cleared 158 of them. The rest, more than 240 projects, are still in some kind of limbo: land cleared but no construction, towers half-built, contracts signed with buyers who have not seen a key, or paperwork stuck somewhere in So Xay Dung (the Department of Construction).

If you are a foreign buyer who already paid a deposit on a Hanoi apartment, or you are thinking about doing so, this deadline matters more than the marketing brochures will tell you. You can read the full piece here: https://bektu.com/blog/hanoi-404-stalled-projects-march-2026-deadline-foreign-buyers.

Why Hanoi went after this list

Hanoi did not produce this list voluntarily. The push came from the Prime Minister's office in late 2025, which ordered both Hanoi and Ho Chi Minh City (often shortened to HCMC or referred to by its older name, Saigon) to publish project-by-project resolution plans. HCMC was given a January 2026 deadline for its own 12 most prominent stalled projects. Hanoi was given a broader March 1, 2026 deadline covering everything off the state budget, which in practice means private developer projects funded by bonds, bank loans, and presale deposits.

The political logic is straightforward. Nationally, around 2,991 stalled projects are sitting on roughly $100 billion of trapped capital. That capital is locked up at a moment when Vietnam wants foreign investment to keep flowing in. The Truong My Lan case at Saigon Commercial Bank, which produced a death sentence and a $27 billion fraud finding, shook foreign investor confidence in the broader system. Cleaning up the project pipeline is partly about money, partly about signalling that the system works.

What "resolution" actually means

There is a polite version of resolution and a brutal version. The polite version is that the developer finishes the building, the People's Committee signs off, and pink books, the slang term for the Giay chung nhan quyen su dung dat, quyen so huu nha o (the legal ownership certificate that proves you actually own the apartment), get issued to buyers. The brutal version is that the city revokes the project, transfers it to another developer, or in the worst case puts it back into the auction pipeline and leaves the original buyers fighting in civil court.

Both versions are happening. Bitexco Group recently transferred its entire stake in Saigon Glory Co., the developer behind The Spirit of Saigon in HCMC's Ben Thanh quadrilateral. That project had been stuck since 2013 and had issued ten trillion dong (about $407 million) in bonds. The transfer was the resolution, but the bond holders did not get their money back on the original schedule. Repayment was extended into late 2026.

In Hanoi, expect similar deals. A new developer takes over, the buyers eventually get the unit, but the original promises about timeline, pricing structure, and sometimes even unit layout get renegotiated. If you paid a deposit four years ago on a tower that has not started construction, your contract may be honoured, transferred, or quietly canceled.

What a foreign buyer should do this week

First, find out if your project is on Hanoi's stalled list. The list is not a single public document. It exists across People's Committee notices, So Xay Dung filings, and the press. The fastest way to check is to ask your lawyer to pull the project's investment certificate and current construction progress reports from the local district office. If your developer cannot, or will not, share these, treat that as a red flag.

Second, understand where your money is. Under the new Real Estate Business Law that came into full effect in 2026, deposits on future residential units are capped at five percent of the total contract value, and the developer cannot collect more than 95 percent of the contract value until the pink book is issued. If you handed over more than that, you may have a claim under the new rules. If your contract predates 2026, the older rules apply and your protection is weaker.

Third, look at the developer's track record across other projects. A developer with one stalled tower is one story. A developer with three or four stuck projects is a pattern. This is the gap that Bektu (https://bektu.com) was built to close. The platform compiles delivery history across Vietnamese developers and flags timing slips, pink book delays, and known disputes. It is not a brokerage and does not sell units. It is a transparency layer, and on a market where the official lists are scattered across half a dozen government bodies, having one place to compare developer performance saves real money.

The Hanoi-specific risks

Hanoi has its own quirks. Foreign buyer demand has been unusually strong. More than 2,800 apartments were sold to foreigners in Hanoi in 2024, more than double the cumulative foreign volume between 2018 and 2022. That demand has pushed prices up sharply in districts like Tay Ho, Cau Giay, and Long Bien, and it has created pressure on the 30 percent foreign ownership cap per building. If your tower is stalled and gets transferred to a new developer, the new developer may have to redo the foreign quota math, which could affect your eligibility to actually take the unit.

The other Hanoi quirk is land clearance. Many stalled Hanoi projects are stuck not because the developer ran out of money, but because the original land use rights were not cleanly transferred from the previous occupants. Vietnamese law requires the developer to complete compensation to displaced households before construction can finish and pink books can issue. A project can look 90 percent built and still be legally frozen because one or two families have not signed off. Ask your lawyer to verify land clearance status, not just construction status.

What to watch between now and March 1

The People's Committee is expected to publish phase-by-phase resolution decisions through the first quarter of 2026. Each decision will name the project, name the developer, name the resolution mechanism, and set a new construction timeline. If your project appears on one of these decisions, read the full text rather than the press summary. The decision often contains conditions, such as the developer must complete a new round of financing within ninety days, that determine whether the resolution actually holds.

If your project does not appear by mid-February, that is also information. It means the People's Committee has not found a viable resolution yet, and the deadline may slip. Vietnamese deadlines on real estate cleanups have a long history of slipping. Plan accordingly.

The bottom line: Hanoi is moving faster than it has in years, but moving fast is not the same as moving cleanly. Read every decision that touches your project, verify with your own lawyer, and treat the official timeline as a starting point rather than a promise.

Sign up to read the rest

Create a free account to keep reading. It only takes a minute.

Developers referenced

Before you commit

Thinking about Bitexco Group?

You cannot walk the land from another country. But you can verify the developer. Bektu contacts them on your behalf and sends you a scored report. They never see who asked.

Verify Bitexco Group anonymously

Thinking about Saigon Glory?

You cannot walk the land from another country. But you can verify the developer. Bektu contacts them on your behalf and sends you a scored report. They never see who asked.

Verify Saigon Glory anonymously

More from Bektu

Stay a step ahead of the wire transfer

Get the occasional note from Bektu on verifying developers before you commit. No noise, just what matters.

We will never share your email. You can opt out at any time.